PPAP Dimensional Results: What to Include and How to Report

November 24, 2026
PPAP Dimensional Results: What to Include and How to Report

PPAP dimensional results are the measured proof that your production parts match the customer's drawing. Every ballooned characteristic gets a line with its specification, its limits, the method used and the actual value from a real sample part. Reviewers reject the submission when the balloons, revisions or sample counts do not line up. The way to avoid that is to build the report straight from the ballooned drawing and the measurement data, so each result is tied to its characteristic. That is what the QA-Report measurement wizard is built to do.

This guide covers element 9 of the 18 PPAP elements: what the report must show, how many parts to measure, how to handle a failing dimension, and how customer requirements differ.

QA-Report
qa-report.com
Link PPAP Dimensions to Measured Results
QA-Report connects ballooned drawing dimensions with measured values and flags out-of-tolerance results for dimensional reporting.
Visit

TL;DR

  • Dimensional results (element 9) list every dimension and note on the design record with its limits, the measurement method, the actual measured value and a pass/fail status.
  • Sample counts depend on the customer: published requirements range from 3 to 6 parts, with parts taken from every cavity or tool in multi-cavity streams.
  • Balloon numbers, part number, drawing revision and sample identification must match across the drawing, the report and the warrant.
  • A result outside the design specification is fixed in the process before submission, not explained away in the report.
  • QA-Report links ballooned drawing dimensions to measured results and flags out-of-tolerance values automatically.

Table of Contents

What PPAP dimensional results prove

PPAP is the Production Part Approval Process, defined by AIAG (the Automotive Industry Action Group). Its purpose, as one OEM supplier training quotes the AIAG manual, is to give evidence that the organization understands all customer engineering design records and that the process can consistently meet them at the quoted production rate.

Dimensional results are the part of that evidence that deals with geometry. The AIAG PPAP 4th Edition (section 2.2.9) asks for proof that the dimensional verifications required by the design record and Control Plan are complete. Results must cover each unique manufacturing process (cells, lines) and all cavities, molds, patterns or dies. Actual results are recorded for all dimensions except reference dimensions, plus the characteristics and specifications noted on the design record and Control Plan.

Two practical points follow from that wording:

  • The report is not a summary. A "pass" stamp without the measured value does not meet the requirement.
  • The report covers the production process, not one lucky part. That is why cavities, lines and cells appear in the requirement.

When is a PPAP requested? Supplier guidelines list new parts or tools, engineering changes, tooling transfers, corrections of discrepancies, material or sub-supplier changes, process changes and manufacturing location changes. Each of these can mean a fresh set of dimensional results.

What the report must contain

The AIAG manual allows several recording formats: the Dimensional Results form in Appendix C, a pictorial, GD&T sheets, or a checked print with results written legibly on the drawing. An optical comparator inspection requires a tracing. Whatever the format, the fields customers ask for are very consistent.

AM General's supplier training says each ballooned feature on the design record needs a line item with the balloon or item number, characteristic description, specification or nominal, upper and lower limits, measurement technique, actual measurement and pass/fail status. It also expects the correct part revision, number and description on every document, signed and dated. Basic and reference dimensions are listed with tolerance shown as N/A.

Seven essential dimensional report fields

TI Automotive's guideline adds the test date, the measurement equipment, OK/NOK qualification and an authorization signature with name, job title and date.

The AIAG manual also requires the report to state the design record date, change level and any authorized engineering change not yet incorporated. Change level, drawing date, organization name and part number must appear on every auxiliary document, such as layout sheets, CMM point results and GD&T sheets. One measured part must be identified as the master sample.

Field checklist for each line item

  1. Balloon or item number that matches the ballooned drawing.
  2. Characteristic description, including any drawing note.
  3. Nominal or specification value.
  4. Upper and lower limits (or N/A for basic and reference dimensions).
  5. Measurement technique and equipment.
  6. Actual measured value for each sample, cavity by cavity.
  7. Pass/fail (OK/NOK) status.
  8. Revision, part number, date and signature on the page.

A measurement strategy is increasingly requested as well. Tenneco's guidelines call for the measuring system, part orientation and clamping, alignment reference system, number of points per measurement, calculation method and the software revision used. Tenneco also accepts only measured values: ranges are not allowed.

How many parts to measure

The AIAG manual does not fix one number for every customer, so you work from the customer's own supplier manual. A sample of what published requirements say:

Customer documentMinimum parts for dimensional results
Guardian Industries checklist (Dec 2022)At least 3 samples from each cavity or tool, with a ballooned drawing
Littelfuse supplier manual (Mar 2021)At least 5 production parts; at least 3 per cavity for multi-cavity molds
TI Automotive guideline (Rev I)At least 5 numbered samples per cavity unless otherwise agreed
AM General training6 sample parts
Ford specifics (Nov 2026)At least 5 parts, individual results, every cavity or tool in multi-cavity streams

The lesson is to read the customer's current document before you plan the measurement run. Measuring five parts when the customer wants five per cavity is a rework cycle you can avoid.

Littelfuse adds a point that is easy to miss: the measured parts must be the same parts you submit as sample parts. Siemens likewise expects you to clearly identify the PPAP samples used for the dimensional results. Serial-number or tag each part before it goes to the CMM, and keep that identity in the report.

Tagged sample parts staged for CMM inspection

Matching measured values to the ballooned drawing

The core of element 9 is traceability: drawing characteristic, measured value, sample part. Break any link and the reviewer cannot follow the chain.

Tenneco requires the balloons on the fully ballooned drawing to match the Dimensional Results report, with an evaluation result for every data point. Guardian asks for the same pairing of ballooned drawing and report.

A reliable routine looks like this:

  1. Lock the drawing revision. Confirm the revision on the customer's design record, and note any authorized engineering change not yet incorporated. The warrant, the report and the drawing must all carry the same level.
  2. Balloon every dimension and note. Number them in a consistent sequence. Missing a drawing note is the classic gap, because the requirement covers notes as well as dimensions.
  3. Define the measurement plan. Decide the method for each characteristic, the datum alignment and the number of points. For position and form callouts, fixture the part the way the datum scheme says; our guide to GD&T datums for inspection teams explains how a wrong setup causes false rejects.
  4. Measure and record actual values. Enter the measured number, never "target" or "nominal", for each sample and each cavity.
  5. Evaluate against limits. Compare each result to the lower and upper limit and mark OK or NOK.
  6. Assemble and sign. Attach the ballooned drawing, auxiliary sheets such as CMM point results, and the signed, dated report.

Done by hand, steps 2 to 5 mean transcribing hundreds of values between a PDF drawing, a CMM printout and a spreadsheet. Each transcription is a chance for a balloon to shift or a value to land in the wrong row. In QA-Report, the measurement wizard links ballooned drawing dimensions to measured results, and automatic drawing ballooning numbers the dimensions for you. CMM data can be imported rather than retyped, and the generated PDF report carries the statistical summary. See how this works in our CMM inspection software.

When a result is out of tolerance

The rule is simple and unforgiving. Siemens states that results not meeting the design specification must be addressed before PPAP submission, and that "Not OK" results typically require changes to the manufacturing process. In some cases the customer may agree to an engineering change instead.

So the working sequence is:

  • Find the NOK values before assembling the package, not after the customer does.
  • Identify whether the cause is the process (tool wear, offset, fixture), the measurement (setup, datum, probe compensation) or the drawing (a tolerance that cannot be held).
  • Correct the process and re-measure a new set of parts, or request a documented engineering change from the customer when the drawing is the issue.
  • Never edit a value, round it into tolerance or substitute a nominal.

Auto-flagging helps here because the problem surfaces the moment data is imported. QA-Report marks out-of-tolerance deviations as results are matched to the ballooned dimensions, so your team sees the failing characteristic while the parts are still on the floor.

Measurement system evidence that supports the numbers

Dimensional results are only as credible as the gauge behind them. Element 8, measurement system analysis, backs element 9. Littelfuse's Level 3 rules say Gage R&R under 10% is acceptable, 10 to 30% is marginal and needs an action plan, and 30% or more cannot be used; the number of distinct categories must be at least 5. A GR&R is required for each measurement device on the control plan.

Ford is more specific still. Its January 2025 specifics require MSA on all gages before the capability study, ANOVA-based Gauge R&R, and results as percent of study variation and percent of tolerance. Variable studies use at least 10 parts, 3 operators and 3 trials. If you submit to Ford, plan the gauge studies before the measurement run. Our Gage R&R study guide walks through the method.

Where dimensional results sit in the submission level

Element 9 is one of 18 elements, and whether it goes to the customer or stays on file depends on the level. NASA's PPAP tutorial confirms that the 18 elements make up a PPAP and that inclusion of each depends on the submission level.

Per AIAG Table 4.1:

  • Level 1: warrant only.
  • Level 2: warrant with product samples and limited supporting data.
  • Level 3: warrant with product samples and complete supporting data.
  • Level 4: as defined by the customer.
  • Level 5: complete data reviewed at the supplier's site.

Level 3 is the default unless the authorized customer representative specifies otherwise, so plan on a full dimensional report. For the full breakdown, see our PPAP levels guide.

The dimensional report should also agree with the neighboring documents. The control plan lists the characteristics, the process flow shows where they are made, and the warrant certifies the whole package. Our PPAP submission checklist covers all 18 elements, and the process flow diagram checklist helps you catch gaps upstream. If you also work to aerospace first article requirements, FAI vs PPAP shows how the two reports differ.

Customer-specific rules to check first

Element 17 means customer requirements sit on top of the AIAG manual. Ford's November 2026 specifics, for example, direct suppliers to record dimensional results in the Prototype or Production Measurement Results section of the APQP/PPAP Evidence Workbook, on GD&T sheets, or on a checked ballooned print. They also include the Annual Dimensional Layout requirement in the Control Plan. The same document asks for Gauge R&R as percent of study variation and percent of tolerance, plus plus or minus two Total Gauge R&R standard deviations, so the uncertainty of a single reading can be weighed against the distance to the specification limits.

A quick pre-submission review:

  1. Download the customer's current supplier manual and any customer-specific PPAP document.
  2. Note the sample count, cavity rule, format and signature requirements.
  3. Confirm the drawing revision with the customer's design record.
  4. Check which measurement strategy fields they want.
  5. Confirm the submission level in writing.

Customers revise these documents, so check the revision date every time rather than reusing last year's template.

Common reasons dimensional results get sent back

Reviewers look first at the links between drawing, measurements and process documents. Most rejections trace back to a short list of causes, each drawn from the requirements above:

  • Revision mismatch between the warrant, the report and the design record.
  • Fewer parts than the customer's minimum, or no parts from some cavities.
  • Balloon numbers that do not match the ballooned drawing.
  • A missing drawing note or tolerance, such as a basic dimension not listed.
  • Values reported as ranges or nominals instead of actual measurements.
  • A sample set in the report that differs from the parts shipped.
  • Datum setup that differs from the drawing's datum scheme.
  • Missing signature, date or measurement equipment.
  • Any dimension outside specification.

Most of these are clerical, and all are preventable with a report built from the ballooned drawing rather than typed in afterward.

Building the report in QA-Report

Our platform is a cloud-based inspection and reporting system for manufacturers, machine shops and quality engineers in aerospace, automotive and medical device production. For PPAP dimensional results, the relevant pieces are:

  • PDF drawing ballooning with AI auto-numbering, plus support for GD&T.
  • A measurement wizard that links ballooned dimensions to measured results.
  • CMM data import and auto-mapping, so results come from the machine.
  • Out-of-tolerance detection and statistical summaries.
  • Professional PDF reports and interactive report sharing with your customer.
  • Batch and serial tracking and a document vault for the supporting records.

Plans are published on the pricing page: Free at $0 per month, Basic at $49.99 per month and PRO at $149.99 per month, with On-Premise and Enterprise options available without published prices. Start on the QA-Report home page to see the full feature set.

QA-Report

If your next PPAP is coming up, build the report from the customer's current requirements and the ballooned drawing, in one place.

Our view: element 9 is a traceability problem

Most teams treat dimensional results as a measuring task. We see it as a traceability task. The measuring is usually done well. What goes wrong is the chain from drawing balloon to measured value to sample part to signed report, which is rebuilt by hand every time.

That is why we built QA-Report around one linked flow: ballooned drawing, measurement wizard, imported CMM data, out-of-tolerance flags and a PDF report that carries the statistics. Each link is created once and reused, so the report matches the drawing because it comes from the drawing.

Our positioning is simple. A central platform, configurable CMM integration for any machine type, cloud or on-premise deployment for sensitive industries, and a multi-language environment, so your inspectors, suppliers and customers work from the same record.

Quality engineers should spend their time deciding whether a process is capable, not renumbering balloons.

Michael Chen

FAQ

What are PPAP dimensional results?

They are element 9 of the 18 PPAP elements: a record of actual measurements for every dimension and note on the design record, with limits, method and pass/fail status. They show that the production process can hold the customer's drawing. Reference dimensions are excluded from the actual-results requirement in the AIAG manual.

How many parts do I measure for PPAP dimensional results?

It depends on the customer. Published requirements range from at least 3 parts per cavity to 5 or 6 parts, and multi-cavity tools usually need parts from every cavity. Check the customer's current supplier manual, and measure the same parts you submit as samples.

What if one dimension is out of tolerance?

Fix it before you submit. The customer's rules generally treat results outside the design specification as something to resolve in the process first. If the drawing itself cannot be held, ask the customer for a documented engineering change, then re-measure.

Is a Level 3 PPAP required to include dimensional results?

Yes, in the normal case. Level 3 is the warrant with product samples and complete supporting data, and it is the AIAG default unless the customer representative says otherwise. Level 1 is the warrant only, and Level 2 carries limited supporting data, so the customer's instruction decides.